# Resistance Welding Audit Under AIAG CQI-15: Supplier Guide

Source: https://www.therness.com/blog/aiag-cqi-11-resistance-welding-audit-automotive-supplier-guide/
Language: en

![Resistance Welding Audit Under AIAG CQI-15: Supplier Guide](https://www.therness.com/assets/images/blog/aiag-cqi-11-resistance-welding-audit-automotive-supplier-guide.webp)

How resistance spot, projection and seam welding are audited under AIAG CQI-15 (2nd edition): scope, the evidence to prepare and a pre-audit checklist.

**Author:** Luca Santoro **Published:** 6 May 2026 **Reading time:** 8 min

- welding
- automotive
- cqi-15
- quality-monitoring
- audit
- resistance-welding

Resistance spot, projection and seam welding at automotive suppliers are assessed with the **AIAG CQI-15 Welding System Assessment**, now in its 2nd edition. A resistance spot weld takes a fraction of a second; a failed assessment can put shipments on hold for weeks. This guide explains what CQI-15 means for a resistance welding cell, the evidence to have ready area by area, and a pre-audit checklist you can work through with your team.

It is a Therness preparation guide. It is not affiliated with AIAG and does not reproduce the workbook’s requirements, questions or scoring scale.

## Which AIAG Assessment Covers Resistance Welding?

AIAG publishes a family of special process assessments, one per process: heat treatment, plating, coating, welding, soldering, molding and others. Welding is **CQI-15**. Searches for resistance welding often land on CQI-11, which is in fact the *Plating System Assessment*, for zinc and zinc alloy electrodeposits, decorative plating, hard chromium, electroless nickel and electropolishing, and its 3rd edition came out in October 2019 ([AIAG](https://blog.aiag.org/updated-cqi-11-special-process-plating-system-assessment-3rd-edition-is-now-available)). It does not cover welding.

AIAG describes the [CQI-15 2nd edition](https://blog.aiag.org/new-publication-alert-version-2-of-the-cqi-15-special-process-welding-system-assessment-is-now-available-at-the-aiag-store), released in November 2019, as an audit “covering all variations of welding” for ferrous and non-ferrous metals. Three changes in that edition matter to a resistance welding shop:

- **Fastener Projection Welding** was added as a process, alongside Magnetically Impelled Arc Butt (MIAB) welding.
- The **job audit questions moved into the Process Tables**, so the shop-floor check and the process requirements are read together.
- A **scoring system** now gives OEMs a numerical measure of compliance that can be tracked over time.

In practice, the resistance processes you are likely to have on the floor all sit inside CQI-15:

- **Resistance spot welding**: body-in-white panels, door assemblies, seat structures
- **Projection and fastener projection welding**: nuts, studs and brackets on stampings
- **Seam welding**: fuel system parts and other joints that must be leak-tight

For the overall structure of the assessment, see our [CQI-15 audit guide](https://www.therness.com/blog/aiag-cqi-15-audit-pass-checklist-welding-system-assessment/).

**Scope check:** CQI-15 assesses the *welding system*: equipment, process control, documentation, people and corrective action. Passing destructive tests is not enough if the plant cannot show the records behind them, for example calibrated force measurement or dressing logs per gun.

## How the Assessment Works, Without the Workbook

You need the AIAG workbook for the actual requirements and rating rules; buy it from AIAG and work from the current edition. What is useful to know before you open it:

- **System level and process level.** Part of the assessment looks at the organisation as a whole (responsibilities, document control, corrective action, training). The Process Tables look at each welding process you run. A plant with spot welding and projection welding prepares the shared system evidence once, and the process evidence for each.
- **Job audit on real parts.** Since the 2nd edition, the job audit questions are part of the Process Tables. Expect the assessor to pick a part number and trace it from the control plan to the weld schedule, the monitoring data and the test records.
- **A numerical result.** The 2nd edition introduced scoring. Read the workbook for how the result is calculated, and your customer’s specific requirements for the minimum it accepts, before you plan the audit.

## The Evidence a Resistance Welding Cell Should Have Ready

The areas below are our own way of organising the preparation for a resistance welding cell. They are not the AIAG headings.

### 1. Weld Schedules and Change Control

The assessor compares the settings in the weld controller (weld current, weld time, electrode force, squeeze and hold time, any up-slope or pulsation) with the approved control plan and the PPAP submission for the part. Every difference must be explained by a documented, approved change. Parameter creep, such as current raised on the night shift to “get the welds to stick”, without a change record is a typical resistance welding finding.

Keep the weld schedule number visible on the controller and in the control plan, so the link between the two can be shown in seconds.

### 2. Parameter Monitoring and Process Data

If the control plan says a parameter is monitored, have the data: per weld or per sample as the plan states, with limits that match the approved process and evidence that someone reviews it. Gaps in the data, limits wider than the approved window and charts nobody has looked at are typical findings.

Know where each value comes from. Weld current and time usually come from the controller. Force is either measured or only set, depending on the gun, and the assessor will ask which.

### 3. Electrode Management

Electrode caps wear and mushroom with every weld, and the contact area grows. Tip dressing restores the face geometry; caps are replaced when they reach their limit. Have ready:

- Dressing frequency defined in the control plan, per gun
- Dressing events recorded per gun and per shift, not per line
- Cap replacement criteria (number of dresses, face diameter or length limit)
- Cap change records traceable to the gun

A body shop with dozens of guns that logs dressing per line instead of per gun cannot show the evidence for any single gun, and that gap is easy for an assessor to find.

### 4. Weld Verification: Destructive and Non-Destructive

- **Test frequency** matches the control plan: first-off, after a cap change, every N parts or every set interval
- **Results recorded** with date, time, gun, part number, operator and disposition
- **Acceptance criteria** (for example minimum nugget or button size per weld class) traceable to the drawing or to the standard your customer specifies, such as AWS C1.1 or ISO 14373
- **Metallographic sections** on file for launches and after significant process changes
- **Ultrasonic spot weld testing**, if used, with qualified operators and reference standards

Frequency is checked separately from results. If the control plan says “one peel test per shift” and the records show one every two days, that is a finding even if every single test passed.

### 5. Calibration and Verification of Equipment

Force gauges, weld current meters, controller verification and test equipment (ultrasonic testers, measuring tools for button size) all need a current calibration or verification status, visible at the point of use or retrievable at the machine. A spare or mobile gauge with an expired label, used in production, counts as much as a fixed one.

### 6. Procedure Documentation and Weld Classes

Every production weld needs a documented procedure: the weld schedule, the materials and coatings it applies to, and the acceptance criteria. Weld maps identify each joint by number and class, so the assessor can go from a joint on the part to its schedule and its test requirement.

### 7. People

Operators, setters, maintenance technicians and the people who change robot programs or controller parameters need documented training for the equipment they work on, with dates and refreshers. Keep the records accessible to the quality team during the audit, not only in the HR system.

### 8. Reaction Plans and Corrective Action

When a monitor alarms, a test fails or a cap is found out of limits, the control plan must say what happens next: containment, which parts are checked back to the last good test, and who decides. A corrective action closes on evidence: the root cause, the changed procedure or limit, and the check that prevents recurrence.

## Pre-Audit Evidence Checklist

Work through it with the quality, maintenance and production leads together. For each area: what to have ready, and a typical gap.

- **Weld schedules.** Have ready: controller settings vs. approved control plan, change records. Typical gap: parameter creep with no change record.
- **Process data.** Have ready: monitored parameters with approved limits and review evidence. Typical gap: data gaps; limits wider than the approved window.
- **Electrodes.** Have ready: dressing log and cap changes per gun, replacement criteria. Typical gap: logged per line, not per gun.
- **Weld verification.** Have ready: test frequency and results traceable to the control plan. Typical gap: frequency lower than planned.
- **Calibration.** Have ready: current status on force, current and test equipment. Typical gap: expired spare or mobile gauge.
- **Procedures.** Have ready: weld schedule, weld map and weld classes per part. Typical gap: weld map not matching the current part revision.
- **People.** Have ready: training records per person and equipment. Typical gap: records not available to the quality team.
- **Reaction plans.** Have ready: defined containment and closed corrective actions. Typical gap: actions closed on intent, not evidence.

## Plants With Both Resistance and Arc Welding

Most automotive suppliers run both. Under CQI-15 that is one assessment with more than one process to cover: the system evidence is shared, while the process evidence is different. Electrode dressing has no arc-welding equivalent; shielding gas, wire feed and arc parameters have no resistance-welding equivalent. Plan the process evidence for each line separately.

For the arc welding cells, inline monitoring can produce part of the process record as a by-product of production, weld by weld. See how [three sensors record the same weld bead](https://www.therness.com/videos/three-sensors-same-weld-bead/) in an arc welding cell, or read about [weld monitoring systems](https://www.therness.com/welding-monitoring-system/). Tie those records to your [ISO 3834 traceability](https://www.therness.com/blog/iso-3834-en-1090-audit-checklist-welding-manufacturers/) and quality management system, so the evidence chain is the same in every cell.

## From Finding to Closed Action

A finding comes with a corrective action plan and a closure date agreed with the customer. Close it on root cause, not on the record: replacing an expired calibration label does not close a calibration finding, while a calibration schedule that prevents the next expiry does.

The fastest way to close is evidence first: show the corrected record, the updated procedure and the check that prevents recurrence, in that order.

### Getting Your Welding Lines Ready for CQI-15?

Tell us which welding processes you run and which records your customer asks for. A Therness engineer will reply on where per-weld thermal and process-data records fit your lines, and where they do not.

 [Talk to an engineer](https://www.therness.com/contact/) [Read the CQI-15 audit guide](https://www.therness.com/blog/aiag-cqi-15-audit-pass-checklist-welding-system-assessment/)

**Therness solution:** [Welding monitoring system](https://www.therness.com/welding-monitoring-system/) — Each weld compared with a reference in the cycle, with anomaly flags and the ISO 3834 / ISO 17635 evidence kept per weld.

Written by **Luca Santoro**  , [founder](https://www.therness.com/author/luca-santoro/)

## Related Therness solution

[AI weld monitoring platformIn-cycle process-drift visibility and durable QC evidence across thermal, visual and parameter signals.](https://www.therness.com/welding-monitoring-system/)

## Frequently Asked Questions

### Which AIAG assessment covers resistance spot welding?

The CQI-15 Welding System Assessment. AIAG describes its 2nd edition, released in November 2019, as an audit covering all variations of welding for ferrous and non-ferrous metals in automotive production and service parts. Resistance spot, projection and seam welding are therefore assessed in the same document as arc welding. Plating has its own, separate AIAG assessment.

### What changed for resistance welding in the CQI-15 2nd edition?

According to AIAG, the 2nd edition added two processes, Fastener Projection Welding and Magnetically Impelled Arc Butt (MIAB) welding, moved the job audit questions into the Process Tables and introduced a scoring system that gives OEMs a numerical measure of compliance. For the rating rules and the requirements themselves, use the AIAG workbook.

### What evidence should a resistance welding cell have ready for a CQI-15 audit?

At least: weld schedules that match the approved control plan, with change records; parameter data for what the control plan says is monitored; electrode dressing and cap-change records per gun; destructive and non-destructive test results at the planned frequency; calibration or verification of force, current and test equipment; documented weld classes and acceptance criteria; and training records for operators, setters and maintenance staff. This list is our own preparation checklist, not the AIAG requirement text.

### Does a plant with both resistance and arc welding need two assessments?

No separate standard is involved: both process families fall under CQI-15. The system-level evidence (responsibilities, document control, corrective action, training) is shared. The process-level evidence is not: electrode dressing has no arc-welding equivalent, and shielding gas or wire feed records have no resistance-welding equivalent.

### Where can I get the CQI-15 workbook?

AIAG sells the CQI-15 Welding System Assessment, in print and electronic formats, exclusively through its own store. This guide does not reproduce the workbook text, questions or scoring scale.

### Share this article

[LinkedIn](https://www.linkedin.com/sharing/share-offsite/?url=https%3A%2F%2Fwww.therness.com%2Fblog%2Faiag-cqi-11-resistance-welding-audit-automotive-supplier-guide%2F) [X / Twitter](https://twitter.com/intent/tweet?url=https%3A%2F%2Fwww.therness.com%2Fblog%2Faiag-cqi-11-resistance-welding-audit-automotive-supplier-guide%2F&text=Resistance%20Welding%20Audit%20Under%20AIAG%20CQI-15%3A%20Supplier%20Guide) Email

## Related articles

![AIAG CQI-15 Audit Readiness Checklist (Free PDF)](https://www.therness.com/assets/images/blog/aiag-cqi-15-audit-pass-checklist-welding-system-assessment.webp)

### AIAG CQI-15 Audit Readiness Checklist (Free PDF)

Free CQI-15 audit-readiness checklist (PDF): the evidence assessors check on control plans, calibration, traceability, CAPs and welder qualification.

[AIAG CQI-15 Audit Readiness Checklist (Free PDF)](https://www.therness.com/blog/aiag-cqi-15-audit-pass-checklist-welding-system-assessment/)

![VDA 6.3 Welding Audit: Scoring Guide & Pass Checklist](https://www.therness.com/assets/images/blog/vda-6-3-process-audit-welding-manufacturing-scoring-guide.webp)

### VDA 6.3 Welding Audit: Scoring Guide & Pass Checklist

VDA 6.3 process audit for welding: scoring method, P-questions breakdown, pass thresholds and audit preparation checklist for welding manufacturers.

[VDA 6.3 Welding Audit: Scoring Guide & Pass Checklist](https://www.therness.com/blog/vda-6-3-process-audit-welding-manufacturing-scoring-guide/)

![ISO 9606-1 Range of Approval: Thickness, Diameter, Position](https://www.therness.com/assets/images/blog/iso-9606-1-welder-qualification-range-of-approval.webp)

### ISO 9606-1 Range of Approval: Thickness, Diameter, Position

Check whether a welder's ISO 9606-1 certificate covers the joint: thickness and diameter ranges, position coverage, material groups, and re-test triggers.

[ISO 9606-1 Range of Approval: Thickness, Diameter, Position](https://www.therness.com/blog/iso-9606-1-welder-qualification-range-of-approval/)