“B31.1 welding requirements” and “B31.3 welding requirements” get typed into the same search box by engineers who assume the two codes are close enough that one set of answers covers both. They are not interchangeable, and the distinction matters before a single weld is made: ASME B31.1 (Power Piping) governs piping in electric power generating stations, geothermal heating systems, and central district heating and cooling systems, while ASME B31.3 (Process Piping) governs the high-temperature, high-pressure, corrosive, and toxic-service piping typically found in refineries and chemical plants. A power plant’s main steam piping is scoped under B31.1; the process piping in an adjacent chemical unit on the same site can be scoped under B31.3. Get the wrong code into your ITP and every downstream qualification, examination, and acceptance decision is built on the wrong foundation.
This guide covers welding, examination, and acceptance requirements under the current ASME B31.1-2024 edition, which revises the 2022 edition on ASME’s standard triennial cycle. Anywhere this guide states an edition-dependent requirement, the edition is named — B31.1 is revised on a regular cycle and a requirement correct in one edition is not guaranteed to be unchanged in the next.
Scope: what puts a piping system under B31.1
B31.1 applies to piping typically found in electric power generating stations, industrial and institutional plants where the piping serves a power or heating function, geothermal heating systems, and central and district heating and cooling systems. It prescribes minimum requirements for the design, materials, fabrication, erection, testing, examination, inspection, operation, and maintenance of that piping. The determining question is not the pipe’s size or pressure class in isolation, but the service the piping is performing and the facility type it sits within — a steam line and a boiler feedwater line inside a power station are squarely B31.1 territory even though a chemically similar line in a different facility type could fall under a different B31 code.
Welding procedure and performance qualification
B31.1 does not write its own welding procedure qualification rules from scratch. Like the other B31 piping codes and the construction sections of the Boiler and Pressure Vessel Code, it incorporates ASME Section IX by reference for Welding Procedure Specification (WPS) qualification, Procedure Qualification Record (PQR) documentation, and Welder Performance Qualification (WPQ). The fabricator qualifies the procedure and the welder under Section IX’s rules, and B31.1 then adds construction-code-specific requirements on top — which joints require what examination, what the acceptance criteria are, and what additional documentation the piping system as a whole requires beyond the individual joint record.
This split is the same one that runs through every ASME construction code: Section IX answers “is this welder and this procedure qualified to make this type of joint,” while the construction code — B31.1 here — answers “given a qualified welder and procedure, what does this specific piping system require in terms of examination, extent, and acceptance.” Confusing the two, or assuming Section IX qualification alone satisfies B31.1’s construction-specific examination requirements, is a common and avoidable audit finding.
Examination methods and extent
B31.1 sets its examination requirements by a combination of the piping’s service classification (normal fluid service versus category M, or other special classifications the code defines) and the specific joint type and material. The code specifies which combination of visual examination and volumetric or surface NDE (radiography, ultrasonic testing, magnetic particle, or liquid penetrant) applies, and at what extent — spot-examination percentages versus full examination — for each service classification. As with every ASME construction code, B31.1 does not leave the extent to the fabricator’s judgment: the applicable clause tabulates the requirement by classification, and the ITP must cite the specific clause and edition it is drawing the requirement from rather than stating a percentage without that reference.
Examination results are evaluated against acceptance criteria the code itself specifies for weld imperfections — porosity, undercut, lack of fusion, cracking, and similar categories — with limits that vary by examination method and joint type. Because those limits are tabulated in the code and are edition-specific, this guide does not reproduce them; an ITP or a welding engineer scoping a job pulls the actual table from the current B31.1-2024 text rather than from a secondary summary, precisely because a table copied out of context loses the qualifying conditions attached to it in the code itself.
Post-weld heat treatment
B31.1 mandates post-weld heat treatment (PWHT) for specific material and thickness combinations, following the same general logic as the other ASME piping and pressure codes: PWHT relieves residual welding stress and, for certain steels, tempers a hardened heat-affected zone that would otherwise be more susceptible to cracking in service. The code’s mandatory PWHT table specifies, by material group (P-Number) and nominal thickness, whether PWHT is required and — where required — the minimum holding temperature range and minimum holding time, all tabulated in the current edition rather than restated here as a standalone figure, since the exact values are grouped by base metal and change between code revisions.
What a fabricator can standardise regardless of edition is the monitoring discipline around the PWHT cycle itself: recording actual part temperature throughout the heating ramp, the hold, and the controlled cool-down, and retaining that record against the specific joint or heat-treatment lot it applies to. Thermal monitoring of the PWHT cycle is how that record gets produced without relying on a single thermocouple reading or an operator’s log entry, and a continuous temperature trace is far more defensible in an audit than a start/stop time and a target temperature written on a traveler.
Interpass temperature control
Separately from PWHT, B31.1 — again through the material and welding procedure requirements it shares with Section IX-qualified procedures — requires interpass temperature to stay within the range the qualified WPS specifies for the base material being welded. Interpass temperature that runs too low increases the risk of hydrogen-assisted cracking in susceptible steels; interpass temperature that runs too high can degrade mechanical properties in the heat-affected zone on multi-pass welds, particularly on higher-alloy materials common in power piping service. Interpass temperature measurement and control covers how that window is verified pass by pass rather than assumed from the ambient shop conditions or a single spot-check early in a multi-pass sequence.
Building the evidence trail
A B31.1 job’s quality evidence has three layers that need to reconcile with each other at final acceptance: the Section IX procedure and welder qualification records, the joint-by-joint welding and examination records the construction code requires, and — increasingly, alongside rather than replacing either — a continuous process record from in-process monitoring during welding and PWHT. A welding monitoring system that captures parameter and thermal data throughout the pass and through any subsequent heat treatment gives a fabricator a per-joint record that supports, but does not substitute for, the code-required qualification and examination documentation. An auditor reconciling a power-piping job’s paperwork is looking for exactly that: qualified procedure, qualified welder, the specified examination performed and disposed against the correct acceptance criteria, and PWHT executed and recorded to the applicable temperature and time window — with process monitoring data as corroborating evidence where a fabricator has it, not as a replacement for any of the four.
Practical scoping checklist
When a piping system’s B31 code assignment is ambiguous — a boundary case between a power station’s own piping and a process system it interfaces with — resolve it before qualification work starts, not during examination. Confirm the facility type and the piping’s service function against B31.1’s own scope statement, check whether the specification explicitly invokes B31.1 or another B31 code, and if genuinely uncertain, treat the piping under the more restrictive of the plausible codes rather than assuming the less demanding one applies. Once the code is settled: qualify procedures and welders under Section IX, pull the current edition’s examination and PWHT tables for the specific material and thickness in front of you rather than relying on a prior job’s numbers, and build the joint-by-joint documentation trail — qualification, examination, PWHT record, and any supporting process-monitoring data — so that a reviewer can trace any single joint back to the specific clause and edition it was built to satisfy.
Pressure testing
Before a B31.1 piping system is placed in service, it is pressure tested — hydrostatically in the majority of cases, with pneumatic testing permitted only where the code allows it and additional precautions apply because of the greater stored energy in a compressed gas test. The code specifies the test pressure as a multiple of the system’s design pressure, adjusted for the ratio between the material’s allowable stress at test temperature and at design temperature, with the exact multiplier and the calculation method set out in the current edition’s testing clause. This guide does not restate that multiplier as a standalone number, for the same reason it does not restate the PWHT table: the applicable value is edition-specific and must be pulled from B31.1-2024 directly against the system’s actual design conditions, not assumed from memory of a prior project or a different B31 code, since the test-pressure basis is not identical across every B31 piping code.
What is consistent regardless of edition is the documentation the test itself needs to produce: the test medium, the test pressure actually achieved and held, the hold duration, ambient and metal temperature during the test, and confirmation that no leakage or visible deformation occurred at any joint. That record becomes part of the same piping system file as the welding, examination, and PWHT records, and a system commissioned without a retrievable test record is functionally unqualified for service even if every individual weld was made correctly.
Repair and rework of rejected welds
A joint that fails examination against B31.1’s acceptance criteria is not automatically scrapped — the code permits repair, but a repair is not simply “reweld it and re-examine.” The repair itself follows a qualified welding procedure (which may be the original WPS if it covers the repair configuration, or a separate repair-specific WPS if it does not), and the repaired area receives the same examination the original joint required, at the same extent, evaluated against the same acceptance criteria. A repair record that only notes “repaired and accepted” without identifying the procedure used and the post-repair examination method and result is not distinguishable, in an audit, from an unrepaired reject that was passed through regardless.
Multiple repair attempts at the same location carry additional scrutiny in most fabricators’ internal procedures, even where the code itself does not hard-cap the number of repair cycles, because repeated heating of the same joint area changes the base metal’s heat-affected zone in ways a single qualified repair does not account for. A quality plan that tracks repair count per joint location, not just per weld number, catches this pattern before a joint has been reworked enough times to introduce a metallurgical risk the original qualification never contemplated.
Where B31.1 and B31.3 boundaries get confused in practice
The clearest boundary cases are auxiliary and interface systems at a power generating facility: fuel oil piping, water treatment piping, or a chemical injection system feeding the boiler water cycle can sit close enough to B31.1’s core steam and feedwater systems that a specification writer defaults to B31.1 without checking whether the fluid service and facility role actually match B31.3’s process-piping scope instead. The reverse error — treating a genuine power-generation piping system as process piping because it superficially resembles piping in a chemical plant — is less common but equally consequential, because it can under-specify the examination extent B31.1 would have required.
The reliable resolution is to trace the piping’s actual service and the facility classification it sits within back to each code’s own scope clause, rather than pattern-matching against piping that looks similar on a different project. When a system genuinely sits at the interface — for example, where a power plant’s process water treatment system transitions into its boiler feedwater system — the boundary point itself should be documented in the project’s piping classification list so that welders, examiners, and auditors are working from the same assignment rather than each inferring it independently.
Documentation retention
B31.1 quality records — WPS/PQR/WPQ documentation, joint welding and examination records, PWHT records, and the pressure test record — need to be retained for a period the owner’s specification or the applicable jurisdictional code typically defines, and in power-generation service that retention period commonly extends for the operating life of the plant rather than a fixed number of years, because a piping failure investigation years into operation may need to trace back to the original qualification and examination records for the specific joint involved. A digital record system that ties process-monitoring data, examination results, and qualification documentation to a specific joint identifier makes that retrieval practical decades later in a way that paper travelers filed by project or by date typically do not.
Document Every B31.1 Joint's Process Conditions
Therness continuous parameter and thermal monitoring gives power-piping fabricators a per-joint process record through welding and PWHT. Book a demo to see it on your own piping systems.
Book a demoTherness solution: Welding monitoring system — Every weld inspected in the cycle, with defect flags and the ISO 3834 / ISO 17635 evidence kept per weld.